Design and replacement of pumping stations

Status: Completed

Object: CPP, Source 2

Location: Chișinău, Moldova

Publication date: 15.12.2023

Design and replacement of 8 pumping stations (C-1250) at Cogeneration Plant in Chisinau, with a total value of $ 3.4 million.

Horus Energy Company replaced condensate pumps with increased productivity at horizontal network heater. The goal was to upgrade the steam turbine PT-80 / 10-130 / 13. Integration with existing equipment was carried out, the foundation was designed for new pumps, and mode adjustment was carried out.

The Ukraine company Nasosenergomash was chosen as the equipment supplier.